Shall, must and should are how a solicitation says what is binding. This page lists the words TenderMatrix reads, the type each one gives a row, which cue wins when a sentence has two, and the cases it gets wrong.

What a shall statement is

A shall statement is a sentence that creates an obligation on a named party, most often a bidder or the successful contractor. In procurement writing the convention is that shall and must are binding, should is desirable, and may is permission. A compliance matrix needs each of them as its own row, because the bid manager has to answer every shall and has to be able to show that none was missed.

The convention is not universal. Some documents define the words in a glossary and some use them loosely. TenderMatrix applies the common convention to every document and shows the word it relied on, so a reviewer can overrule a row in seconds.

The words that decide a row's type

These are the cue lists the converter applies. The Signal column in your matrix shows the cue that decided each row.

Mandatory

WordingExampleSignal
shallThe Contractor shall provide a service desk.shall
shall not, must notThe Contractor shall not subcontract without written consent.shall not
mustTenderers must hold ISO 9001 certification.must
is / are required to, obliged toPersonnel are required to hold clearance.required to
is / are requiredProof of insurance is required.is required
has to, have to, need to, needs toThe supplier needs to confirm stock levels weekly.has to
is mandatory, is essential, is compulsory, or the word mandatoryAttendance at the site visit is mandatory.mandatory
may not (lower case)Bidders may not contact evaluators during the process.may not
will followed by an action verb such as provide, deliver, ensure, maintain, submit, complyThe Offeror will provide a named project manager.will provide

Desirable

WordingExampleSignal
shouldThe system should support single sign-on.should
is / are expected toBidders are expected to attend the briefing.expected to
desirable, highly desirableExperience in the education sector is desirable.desirable
is / are encouraged, recommended, preferred, desiredJoint bids are encouraged.encouraged
preferably, ideally, preferredIdeally, the platform integrates with Jira.preferred
nice to haveOffline mode is nice to have.nice to have
would be an advantage, beneficial, welcome, valued, a plusTraining would be an advantage.would be an advantage
ought toThe design ought to follow the style guide.ought to
the Authority (or buyer, client...) would like, prefers, expects, encouragesThe Authority would like weekly updates.would like

Informational

WordingExampleSignal
optional, optionallyPhase 2 is optional.optional
may (see the note below the table)Bidders may submit a variant bid.may
for information, for reference, for awarenessThis section is for information only.for information
please note, note that, N.B.Please note that the portal closes at noon.note
is / are permitted to, allowed to, entitled to, free toBidders are permitted to attend by video.permitted
at the sole discretionExtensions are granted at the sole discretion of the buyer.discretion
a buyer as the subject with shall, must, will or shouldThe Authority shall provide access to the site.buyer: shall

Question

WordingExampleSignal
the sentence ends with a question markDo you hold ISO 27001 certification?ends with ?
opens with Describe, Explain, Outline, Detail, State how, Confirm whether, Identify how, How do..., What is...Describe your approach to onboarding.starts with describe

Notes on the cue lists

  • Should is not read as Desirable when it is conditional: Should the Contractor fail to deliver, ..., if the system should fail and it should be noted are not preferences.
  • May counts as Informational inside numbered clauses, list items and tables, and in a sentence that opens with a bidder-type subject (Bidders may...). A buyer right such as The Authority may terminate produces no row at all.
  • Will followed by an action verb is Mandatory. The action verbs are provide, deliver, supply, ensure, maintain, submit, comply, perform, support, implement, meet, demonstrate, include, offer, furnish, notify, report, host, train, install, configure, guarantee, warrant, certify and a few more of the same kind.
  • Mandatory as a word counts, but non-mandatory and not mandatory do not.

Tags and table flags

Some RFPs mark the type themselves. A tag at the start or end of a sentence overrides every wording cue, and a flag column in a requirement table decides the row.

TagExampleType
(M) or [M] at the start or end of the sentenceSingle sign-on support (M)Mandatory
(D) or [D]Single sign-on support (D)Desirable
(O) or [O]Single sign-on support (O)Informational
Column headerCell valuesType
M/D/OM, Mandatory, Must, Shall, Essential, Required, Critical, Compulsory, PassMandatory
M/D/OD, Desirable, Should, Preferred, Recommended, ImportantDesirable
M/D/OO, Optional, May, Info, N/A, ReferenceInformational
Mandatory?Y, Yes (only under a Mandatory or Required header)Mandatory
Mandatory?N, No (only under a Mandatory or Required header)Desirable
PriorityHigh, Highest, 1, P1, Critical (under a Priority header)Mandatory
PriorityMedium, 2, P2Desirable
PriorityLow, 3, P3Informational
MoSCoWMust haveMandatory
MoSCoWShould haveDesirable
MoSCoWCould have, Won't haveInformational

A table row is typed in this order: its flag, then its own wording read like any sentence, then the heading above the table. If none of those decides it, a column headed Question gives Question and a column headed Criteria gives Informational. A row that is still undecided is listed as Mandatory, with a note on the row and a warning on the desk, because an unflagged row in a requirement table is more often binding than not. Check those rows first.

The heading rule also applies outside tables. List items and short clauses with no modal verb that sit under a heading such as Mandatory requirements, Desirable, Optional or Questions for bidders take that heading's type, with the signal heading: mandatory (or desirable, informational, question) and a note on the desk.

When a sentence has more than one cue

The first match in this order decides the type.

  1. An explicit (M), (D) or (O) tag.
  2. The buyer as the sentence's subject with shall, must, will or should: Informational. A buyer may produces no row.
  3. A sentence that ends with a question mark: Question.
  4. A mandatory cue.
  5. Will followed by an action verb: Mandatory.
  6. A desirable cue.
  7. An informational cue.
  8. A question opener such as Describe or Explain: Question.

So The vendor shall provide training and should offer a manual is Mandatory, and Describe how the Contractor shall manage risk is Mandatory too, with the row also marked as asking for a written answer. A cue beats a question opener, but not a question mark.

A worked example

This clause group goes in:

## 4. Service levels

4.1 The Contractor shall maintain a service desk available 24 hours a day.

4.2 The Contractor should offer a named account manager.

4.3 The Authority shall provide access to the site within 5 working days of award.

4.4 Bidders may propose a variant bid.

4.5 Describe how the Contractor will escalate a failed fix.

4.6 Response time: 4 hours for priority 1 incidents.

This is what comes out. The table is produced by the same code the converter runs.

ClauseTextTypeSignal
4.1The Contractor shall maintain a service desk available 24 hours a day.Mandatoryshall
4.2The Contractor should offer a named account manager.Desirableshould
4.3The Authority shall provide access to the site within 5 working days of award.Informationalbuyer: shall
4.4Bidders may propose a variant bid.Informationalmay
4.5Describe how the Contractor will escalate a failed fix.Questionstarts with describe
4.6Response time: 4 hours for priority 1 incidents.No rowno modal verb, nothing to read

Clause 4.6 is a real requirement and it produces no row. That is the main way the method fails, and it is why the Mandatory rows are a first pass to read against the RFP, not a substitute for reading it.

From PDF to typed rows

  1. Mark the pages If the converted text carries page markers, rows get a page number. Running headers and page footers that repeat on every page are removed first.
  2. Set aside contents pages Contents entries, dot-leader lines and footer lines are skipped and counted, so they never become requirements.
  3. Read the structure Headings, clause numbers (3.2.1, C.3.1), sub-items ((a), (1), (i)) and the document's own IDs (REQ-101, Q4) give every sentence a section.
  4. Read the tables A table with a Req ID, Requirement or M/D/O column becomes one row per table row, keeping the table's own IDs and flags. Other tables, such as price schedules, are left alone.
  5. Classify each sentence Each sentence is checked against the cue lists on this page, in the order shown below, and the first match decides the type. The matched word is kept in the Signal column. A row with no cue takes the type of the heading above it, when that heading names one.
  6. Expand lists When a clause with a modal verb introduces a list, each list item becomes its own row, typed by the lead-in.
  7. Merge, trim and count Identical wording that repeats is merged into one row with a note. Text longer than 600 characters is cut with a visible note. Totals by type and by section are counted.

Where the rules go wrong

  • No modal verb, no row. Specifications written as facts (Response time: 4 hours, Delivery within 30 days) are missed unless they sit in a requirement table, under a lead-in with a modal verb, or under a heading that names a type.
  • Conditions stay in the text. If the Contractor subcontracts, it shall notify the Authority is one Mandatory row. The condition is not modelled, so read it before you mark the row not applicable.
  • Cross-references are not followed. The Contractor shall comply with Schedule 4 is one row. Schedule 4's own obligations become rows only if Schedule 4 is part of the PDF you uploaded.
  • Buyer duties that do not open the sentence. Following award, the Authority will provide access can be typed Mandatory, because the buyer check looks at the start of the sentence.
  • Two obligations in one sentence stay in one row. Split them in Excel if your owners differ.
  • Notices that use should. Bidders should note the closing date is typed Desirable, because the word should is there. Delete such rows in Excel.
  • Defined terms. A glossary that redefines shall or should is not read.
  • Headings can mislead. A row typed from its heading is only as good as the heading. The Notes column and the desk's notes say when it happened.
  • English only. The cue lists are English.
  • Page numbers exist only when the converted text carries page markers.
  • Long clauses are cut at 600 characters with a note and the source line.
  • Scans and multi-column layouts. Reading order errors can join sentences from two columns, and a misread word can hide a shall. Check scanned documents row by row.

By hand, by text search, or with typed rows

Finding the shall statements three ways
What you need Manual highlighting Generic PDF-to-text TenderMatrix
Finding every shall Read and highlight. A tired reader on page 140 misses some. Search for the word shall, one hit at a time. Every sentence is checked against the same cue list, so the same wording gets the same type every time.
Consistency between reviewers Two readers type the same sentence differently. No typing at all. One rule set. The Signal column shows which word decided each row.
Prohibitions Easy to skip as 'not a requirement'. Found only by searching for shall not. shall not and must not are kept as Mandatory rows.
Buyer obligations Mixed in with the bidder's duties. Not separated. A sentence that opens with the buyer as its subject is typed Informational, so it does not inflate the mandatory count.
A requirement with no modal verb Caught if the reader is careful. Missed. Missed, unless it sits in a requirement table, under a lead-in that has a modal verb, or under a heading that names a type.
Audit trail Your highlighting. None. Section, page when known, source line and signal on every row.

Questions bid teams ask

What is a shall statement?

A sentence in a solicitation or contract that creates an obligation, usually by using the word shall. In most procurement documents shall marks something binding, should marks something desirable, and may marks permission. The convention is common but not universal, which is why a document's own definitions section outranks any tool's default.

What is the difference between shall, must, should and may in an RFP?

Shall and must are binding on the party named as the subject. Should is a preference that is often scored but not required. May grants permission and does not oblige anyone. TenderMatrix types the first two as Mandatory, the third as Desirable and the last as Informational.

How does TenderMatrix find shall statements in a PDF?

The PDF is converted to structured text, then the text is read sentence by sentence against a fixed list of cues, with tables and lists read as rows. The steps and the cue lists are on this page. There is no language model deciding a row's type, which is why the same text always gives the same rows.

Is will treated as a requirement?

Only when it is followed by an action verb such as provide, deliver, ensure, maintain, submit or comply, and the sentence does not open with the buyer as its subject. The Contractor will provide weekly reports becomes a Mandatory row with the signal will provide. The Authority will review proposals becomes Informational.

Why is a sentence starting The Authority shall marked Informational?

Because it binds the buyer, not you. Those rows stay in the matrix so dependencies and assumptions are visible, but they are not counted as mandatory work. A buyer duty that does not open the sentence, such as Following award, the Authority will provide access, can be typed Mandatory by mistake. Filter Mandatory and read it.

Can it find requirements that have no shall or must?

Not from plain prose. Response time: 4 hours and Delivery within 30 days contain no modal verb, so they produce no row. They are found when they sit in a requirement table, in a list under a lead-in that has a modal verb, or under a heading such as Mandatory requirements, where they take the heading's type. Read the RFP's specification sections for statements like these.

What if the RFP defines shall and should differently?

The rules do not read a definitions section. If the document says that should is mandatory, or that shall applies only to the supplier's subcontractors, treat the Type column as a starting point and change it in the downloaded file. Type is not editable in the browser desk, which edits Owner and Status.

What does the Signal column show?

The word or flag that decided the row's type: shall, must, will provide, should, M, High, ends with ?. It lets a reviewer see why a row was typed the way it was and spot a wrong call quickly.

How accurate is the extraction?

We do not publish an accuracy percentage, because it depends on how the RFP is written. Documents with numbered clauses and clear modal verbs come out well. Documents with requirements in running prose, scans, or multi-column layouts need more checking. Every row shows its source line so you can verify it.

Does it work in languages other than English?

No. The cue lists are English. A document in another language will produce few rows, mostly from tables with M/D/O style flags, and the notes on the desk will say how many sentences were checked.

Are shall not and must not kept?

Yes. A prohibition is an obligation, so shall not and must not become Mandatory rows with those words as their signal. A lower-case may not is also read as Mandatory.

How much of an RFP can I check for free?